What This Article Covers

NEC 314.16 is the box fill calculation rule. It tells you how many cubic inches of capacity a box needs based on what's inside it — conductors, devices, internal clamps, and grounding wires.

Key Requirements

  • Each conductor passing through or terminating in the box = 1 conductor of its own size
  • Each grounding conductor (or bundle of grounding conductors) = 1 conductor of the largest grounding conductor present
  • Each yoke = 2 conductors of the largest size connected to it
  • Internal cable clamps (one or more) = 1 conductor of the largest size in the box
  • Multiply the conductor count by the volume allowance in Table 314.16(B)

Common Field Applications

  • Sizing a switch box that contains 12 AWG, two cables, and a single switch
  • Verifying a junction box has capacity for a 6-cable splice
  • Sizing a deep box for a multi-circuit switch installation

Common Mistakes & Inspection Failures

  • Adding individual ground wire fill instead of one largest
  • Forgetting yoke fill counts as 2
  • Using the wrong volume allowance row

Related NEC Articles

Have a specific question about NEC 314.16?

Ask Sparky AI for a plain-English answer with citation.

Ask Sparky AI

Frequently Asked Questions

What does NEC 314.16 cover?

NEC 314.16 is the box fill calculation rule. It tells you how many cubic inches of capacity a box needs based on what's inside it — conductors, devices, internal clamps, and grounding wires.

What are the key requirements of NEC 314.16?

Key requirements include: Each conductor passing through or terminating in the box = 1 conductor of its own size; Each grounding conductor (or bundle of grounding conductors) = 1 conductor of the largest grounding conductor present; Each yoke = 2 conductors of the largest size connected to it. See the full requirements list on this page.

What are common mistakes with NEC 314.16?

Adding individual ground wire fill instead of one largest Forgetting yoke fill counts as 2 Using the wrong volume allowance row

Related Resources

Michael — IBEW Local 134 Journeyman Electrician and pre-apprenticeship instructor

Michael B.

IBEW Local 134 Journeyman · Licensed Contractor · IL Educator

Michael started in the IBEW at 18 and made foreman as a 3rd-year apprentice. Thirteen years in, he’s a Local 134 journeyman, a licensed electrical contractor, a licensed Illinois teacher, and OSHA 30 and EPA 608 certified. He teaches a federally recognized pre-apprenticeship on the south side of Chicago — where he’s helped 100+ students get into the IBEW. He built Sparky AI around exactly what the NJATC exam tests and what trips people up. Prep with this and you walk in ready.

13-yr journeymanLicensed contractorLicensed IL teacherOSHA 30EPA 608100+ into IBEW
More about Michael →